Construction of wood chip boiler house with moving grate technology in “Salaspils Siltums”

Date of realization
26.09.2011
Contract No.
L-PCS-11-0023
Source of funding
Investment and Development Agency of Latvia, European Union Cohesion Fund.
The aim of the project is to build a 7 MW wood chip boiler house, introducing renewable energy resources in the production of thermal energy. The eligible costs of the project are 1,123,371.62 LVL, Cohesion Fund support is 561,685.81 LVL. The construction contractor is SIA "Merks".
The aim of the project is to build a 7 MW wood chip boiler house, introducing renewable energy resources in the production of thermal energy. The eligible costs of the project are 1,123,371.62 LVL, Cohesion Fund support is 561,685.81 LVL. The construction contractor is SIA "Merks".
Project no.
PCS/3.5.2.1.0/10/02/028